One of the unintended consequences of load shedding is that when the power is turned back on in an area, most geysers switch back on at the same time and work hard to reheat water that had cooled, leading to sudden surges in demand.
This is called ‘comeback load’, and a new study shows that this phenomenon pushes up maximum geyser energy consumption across some areas by 90%. Considering that geysers are responsible for approximately half of household electricity use, this creates havoc for local municipalities and the grid operator, and impacts consumers as well.
Implications of Comeback Load
Comeback load directly increases electricity costs for large consumers – including municipalities, residential estates, apartment blocks, and retirement villages – who often pay charges based on their maximum demand levels each month.
Ironically, this means that power cuts ultimately translate into higher household energy bills. As per Eskom’s Megaflex tariff, which applies to municipalities and large customers such as estates, this comeback load could drive up electricity costs by about R1,300 per geyser per year.
Comeback load, meanwhile, is also damaging electricity distribution networks because it can trip or overload transformers, substations, and other critical infrastructure. Again, this raises system costs and leaves the grid in a more fragile state.
To mitigate the impact of comeback load, some municipalities are carefully sequencing how they return power to individual substations and the areas they serve. While this tempers maximum demand, it does result in extended load shedding periods and higher operational costs.
Further, many municipalities grapple with the problem of which areas to switch back on first, as there are often complaints about inequity and unfairness. In some towns, the last area can be switched on up to two hours after the first, because technicians have to physically drive between substations to switch the power back on.
A recently concluded pilot project showed that there is a better way to deal with this problem.
Project Smart Geyser: A Solution in Action
Under Project Smart Geyser, a 30-month-long study, Plentify partnered with the City of Cape Town, Hessequa Local Municipality, residential estates and retirement villages to gauge what impact artificial intelligence-enabled geyser-management devices would have on curbing comeback load and trimming household energy bills.
We installed 500 of these devices, called HotBots, in households around the municipalities and in multi-family properties. They were coordinated in such a way that the geysers drew power at slightly different times from one another, only turning on those geysers that actually needed to serve hot water, and avoided using energy at the worst times for the grid. This was done only to the extent that homes still had a reliable supply of hot water.
Backed by German development agency GIZ and clean energy financing facility EEP Africa, and with independent oversight from the University of Cape Town’s Measurement and Verification Inspection Body, the study found that the HotBots eliminated comeback load after bouts of load shedding – and went further than that to flatten maximum demand to a point much lower than even without load shedding.
The devices reduced each geyser’s electricity use during peak periods by up to 80%, and cut maximum demand at any point in time across the entire fleet of water heaters by up to 60%.
This slashed demand charges roughly in half, and yielded substantial energy cost savings for participating households, while ensuring that all participants still had hot water when they wanted it.
The project also demonstrated how these devices, when coordinated, can prevent damage to distribution infrastructure and defer the need for major investments in substations and transformers. In fact, with intelligent control, roughly twice as many geysers could be connected to the grid without placing any more strain on infrastructure.
This is illustrated in the chart below, which shows daily maximum demand before the installation of HotBots in purple, and after installation in teal. Not only did HotBots mitigate the biggest spikes in maximum demand, but they also flattened maximum demand, making it much more stable and predictable.
At a broader scale, this solution assists the national grid operator by enhancing the predictability of demand. In turn, this will translate into reduced unplanned outages caused by tripping.
Sustainability and Cost Savings
This homegrown solution to comeback load carries a number of other advantages.
By shifting geyser energy use away from peak hours – while still ensuring households have hot water when they need it – these devices can reduce strain on the grid during the early mornings and evenings, when Eskom often has to rely on expensive diesel generators to meet demand.
In a city such as Cape Town, installing these devices in just a quarter of households could cut load shedding in the mornings and evenings by a cumulative 20 hours every month, the study found.
At the same time, this solution helps to address the cost of living crisis by improving each geyser’s overall energy efficiency by up to 24%, simply by switching them off when they do not need to be consuming electricity.
It is a truly holistic demand management solution that has proven its worth, and we look forward to playing a meaningful role in restoring energy security in South Africa.
- About the author:
- Jon Kornik is the CEO of Plentify, with a background in energy, technology, and finance. Previously, he led Google’s energy business in Africa, overseeing the funding of major wind and solar farms and developing technology solutions for energy expansion. Jon has also worked as an independent energy and sustainability consultant, aiding the South African government in attracting international investment for renewable energy and assisting Nike in enhancing supply chain sustainability. Furthermore, he established and managed the African office of South Pole Group, a carbon finance and climate consulting firm, and consulted for McKinsey & Company in mining and energy.
- Key focus areas of the content piece –
- It addresses the detrimental effects of power surges following load shedding, and delves into a pressing issue that’s often overlooked: the phenomenon of ‘comeback load.’ As power is restored after load shedding, geysers kick in simultaneously, causing sudden spikes in energy demand. This not only strains local municipalities and grid operators but also leads to increased electricity costs for consumers.
- Jon also unpacks the results of Project Smart Geyser:
- A 30-month-long study conducted in partnership with the City of Cape Town, Hessequa Local Municipality, and other stakeholders, where Plentify introduced HotBots, AI-enabled geyser management devices. These devices, coordinated to optimise energy usage, effectively eliminated comeback load and significantly reduced maximum demand.
- The results speak for themselves: HotBots reduced peak period electricity consumption by up to 80% per geyser, cut maximum demand by up to 60% across the board, and slashed demand charges in half. Moreover, by smoothing out demand fluctuations, these devices contribute to a more stable and predictable grid, reducing the likelihood of unplanned outages.